STEP 1: PREPARE WALL BASE
Figure the location, length and
elevation of the wall. Excavate base trench approximately 9" deep and
60" wide. Using 1/2" 3/4" crushed stone, recycled concrete or gravel,
compact to 95% Standard Proctor or greater. Always start wall base at
the lowest elevation of the wall. Keep in mind that LondonBoulder units
can be directly off-loaded from the delivery boom truck if desired.
However, this can be time consuming and costly if wall base is not
adequately prepared.
STEP 2: INSTALL THE BASE COURSE
Place and level each base course unit, making sure unit is level from
side to side, front to back, and with adjacent units. The base course is
critical for achieving desired results. Take time accordingly.
STEP 3: DRAIN PIPE INSTALLATION
Install a 6" wrapped, perforated drainpipe behind the base course and
along the full length of the wall. Surround drainpipe with 1 sq. ft. of
drain stone.
STEP 4: BACKFILL
Use 3/4" to 1" free-draining, angular,
granular fill to a width of 6" behind the wall. Compact to a 95%
density. Round rock and pea-gravel should not be used.
STEP 5: INSTALL ADDITIONAL COURSES
Clear all rock and debris from the top of
each row before installing next course. Position additional courses upon
preceding layer, straddling the two lower units and staggering the
vertical joints.
*NOTE FOR PARTITION WALLS:
If installing a partition wall, a definite
pattern must be used. This requires that the installer adhere to a
specific set of wall lengths as determined by full-unit increments. All
partition walls should have a base course consisting of full and
full-corner LondonBoulder units. The second course will consist of full
units encased by a half-corner block on one end and a 2/3-corner block
on the other. All subsequent rows will repeat the pattern created by the
first two courses. Please contact your LondonBoulder salesperson with
any questions.
*NOTE: FOR WALLS GREATER THAN 9¹ TALL,
PLEASE CONSULT A CERTIFIED ENGINEER.
|